Mark each scope item as included, excluded, provisional or unclear. Rows with different selected statuses are highlighted for written follow-up.
20 rowsConstruction, professional and commercial scope
3 quotesA consistent comparison surface
PrivateEntries stay in this browser page
Comparison status
No selected scope differences yet.
Swipe sideways to compare Quote B and Quote C.
Scope item
Wall system and dimensions
Design basis and drawings
Engineering and certification
Authority applications and fees
Excavation and founding
Existing-wall demolition
Spoil removal and disposal
Temporary support and site protection
Drainage aggregate and geotextile
Subsoil pipe and outlets
Backfill and compaction
Material finish and capping
Fence, pool or structure interfaces
Clean-up and reinstatement
GST
Provisional sums and adjustment method
Programme and payment stages
Variation approval
Warranty and defects process
Handover records
Resolve differences in writing
A highlighted row is not automatically a problem. It tells you the proposals are not yet like for like. Ask each provider to confirm the scope, price effect and variation method before acceptance.
How to use the checker
Copy only what each written proposal actually says.
Use unclear where the proposal is silent or ambiguous.
Ask written questions and update the status from the response.
Compare the GST-inclusive total only after the important rows align.